GENQ tracks 78 Iraqi projects worth $217.9 billion of which three are complete, while the state that must fund a quarter of them spent 236 billion dinars on capital expenditure in the whole of May 2026, an 87 percent fall against the 2025 monthly average.
Announced value and executed value are different currencies, and in Iraq the exchange rate between them is unpublished. A reader deciding whether to bid, supply or lend needs to know which projects have money behind them, who is being paid and how late. One arithmetic runs through everything below: the tracker holds $53.2 billion of publicly funded projects, and May 2026 capital spending was IQD 236 billion.
| Stage | Projects | Tracked value, USD bn | Share of value |
|---|---|---|---|
| In progress | 50 | 152.91 | 70.2% |
| Announced | 19 | 58.35 | 26.8% |
| Completed | 3 | 6.54 | 3.0% |
| Awarded | 6 | 0.14 | 0.1% |
The awarded category holds six projects and $140 million because five of the six carry no published contract value: Kirkuk, Basra and Saladin oil and gas packages involving BP, Halliburton and HKN Energy. The whole $140 million is one Middle Euphrates transmission contract. Announced holds $58.4 billion, a stage that in Iraq has meant a memorandum rather than a funded commitment, and the $17.0 billion Development Road and $17.0 billion Baghdad Metro are 58 percent of it.
Three completions total $6.54 billion: the $6.04 billion Karbala Refinery built by Hyundai Engineering and Construction, the $0.50 billion federal export pipeline rehabilitation delivered by the State Company for Oil Projects, and the Al-Nour solar panel production plant in Karbala, which carries no published value. Both valued completions were publicly funded.
Eight tracked projects announced before 2020 are still in progress: Grand Faw Port dates to 2006, Bismayah New City, the $10.0 billion Hanwha Engineering and Construction development outside Baghdad, to 2012, Rumaila's redevelopment to 2009, the Baghdad water and sewerage project to 2018 and the Basra electricity dissemination project to 2019. In progress is a category a project enters and does not reliably leave. Only six projects, 7.7 percent, carry an expected completion date. Two fall in 2026, and one of those, the Basra electricity dissemination and development project due 30 June 2026, is still in progress as at 10 August.

5,024 words, 7 charts, every figure sourced and dated.
You have read the opening section. The rest continues for another 4,124 words.
This is one of three GENQ flagship analyses. Request access and we will send the full report, along with the underlying figures.
This figure updates with the GENQ Sector Vitality Radar. The analysis above was written against the reading on 12 August 2026, so the two may differ.